LABOR INTELLIGENCE · WEEKLY SNAPSHOT Week of October 16, 2026 Figures as of Oct 15, 01:25 UTC
America’s AI Buildout
What employer hiring shows about the U.S. buildout of AI data centers and chip fabs: where the projects stand, what work they need and where it is. Every Friday we save that week’s edition.
58 of 85 tracked projects aren’t operating yet: 44 under construction, 11 in development and 3 announced.
32% of openings list travel, per diem, relocation or housing.
19% of openings are in three metros: Northern Virginia, Phoenix metro and Dallas–Fort Worth.
Where the buildout stands
85 sourced projects by stage
- Announced 3
- Development & approvals 11
- Under construction 44
- Operating, with expansion 18
- Operating 9
Openings by phase of work
- Planning & design 13%
- Construction 24%
- Commissioning 4%
- Operations 28%
- Other roles 30%
Each opening counted once, by the phase of work its job title names.
Data centers and chip fabs
- Data centers 95% 3,335
- Chip fabs 5% 189
Where the work is
Trades most in demand
Share of all 3,524 openings. An opening can involve more than one trade.
Most openings by market
| Market · most common work | Openings | Travel or per diem | 7 days in / out |
|---|---|---|---|
| Northern VirginiaFacilities & fab operations 52% · Electrical 13% | 289+1 −1 in 7 days | 23%67 openings | +1 −1 |
| Phoenix metroFacilities & fab operations 42% · Construction leadership 19% | 192+5 −4 in 7 days | 20%39 openings | +5 −4 |
| Dallas–Fort WorthFacilities & fab operations 32% · Construction leadership 26% | 187+5 −5 in 7 days | 26%49 openings | +5 −5 |
| Central OhioMechanical & HVAC 26% · Facilities & fab operations 26% | 146+0 −0 in 7 days | 32%46 openings | +0 −0 |
| Atlanta metroConstruction leadership 39% · Facilities & fab operations 27% | 143+2 −12 in 7 days | 38%55 openings | +2 −12 |
| Upstate South CarolinaMechanical & HVAC 20% · Electrical 17% | 125+0 −0 in 7 days | 34%43 openings | +0 −0 |
| Chicago metroFacilities & fab operations 53% · Construction leadership 36% | 81+0 −0 in 7 days | 11%9 openings | +0 −0 |
| Denver metroConstruction leadership 26% · Electrical 14% | 78+3 −1 in 7 days | 29%23 openings | +3 −1 |
| Boardman–HermistonFacilities & fab operations 46% · Electrical 24% | 68 | 68%46 openings | — |
| Abilene regionConstruction leadership 40% · Facilities & fab operations 16% | 50 | 64%32 openings | — |
In / out counts postings that appeared or came down at the employers we watched all seven days (14 of 60 employers). Employers we start tracking join after a full week, so added coverage never shows as new openings.
Latest project news
Newest first, by date of the announcement. All news →
- Oct 2, 2026 · Operations StartApplied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1Applied Digital Polaris Forge 1 · Ellendale
- Sep 28, 2026 · Project AnnouncementCrusoe Developing Data Center Campus in Armstrong County, TexasAmarillo, TX
- Sep 14, 2026 · Operations StartCrusoe Opens Second Tulsa Manufacturing Facility, Expanding Production of Critical AI Infrastructure ComponentsTulsa region
- Sep 11, 2026 · Construction MilestoneEdged US Celebrates Topping Out of OMA01-1 and OMA01-2 in Council BluffsOmaha
Coming up
The next dated project targets, as owners, builders and agencies publish them. A target is not a confirmed outcome.
- Target · October 2026Stargate Abilene Permanent transformer replacements completeAbilene, Texas
- Target · November 2026EdgeCore Ashburn AS01 / AS02 AS01 initial occupancySterling, Virginia
- Target · June 1, 2027CyrusOne Medina County SAT14A estimated completionNear Castroville, Medina County, Texas
- Target · June 15, 2027Vantage San Antonio (Rogers Road) TX22 estimated completionSan Antonio, Texas
These are postings on the employer career sites we monitor, not every vacancy, hire or filled job, and projects we have sourced, not every project. Coverage is selective: see what we cover.