Projects

Follow data-center and semiconductor projects from planning through operations.

Updated Oct 17 · 12:08 PM UTC 45-day coverage window Coverage
OperatingCanton, Mississippi

AWS Canton (Madison County Mega Site)

Amazon announced two Madison County campuses in January 2024 and broke ground in May 2024; Gray describes its construction of a $1.6 billion AWS data-center campus in Canton. Amazon reported in August 2025 that its Madison County project had a first section operational, without naming the campus. Entergy Mississippi agreed in March 2024 to serve the two data centers.

Developer
Amazon Web Services
Scale
Investment
$10B announced in 2024 for Amazon's two Madison County campuses; Gray describes its Canton campus work as $1.6B
Observed hiring
23 employer openings in this market
Verified Oct 14, 2026View project →
Operating + constructionHermiston, Oregon

AWS Hermiston PDX138

The City of Hermiston reports that this Amazon Data Services campus broke ground in 2023 and received its first certificate of occupancy in July 2024, with 83 jobs reported for 2025. City permits on the same parcel name Gray as builder of the data-center shells and fit-outs and OEG for electrical wiring, and further buildings were permitted through 2026.

Developer
Amazon Web Services
Scale
215,000 sq ft data-center shells
Investment
About $3.1B reported to the city through 2025 (not assessed value)
Observed hiring
65 employer openings in this market
Verified Oct 14, 2026View project →
Under constructionHermiston, Oregon

AWS Hermiston PDX245

The City of Hermiston reports that this Amazon Data Services campus broke ground in 2024 and had no certificate of occupancy by the end of 2025. City permits name Balfour Beatty for the first data-center shell (February 2025) and Dynalectric for its temporary electrical service; shell permits for further buildings followed into 2026.

Developer
Amazon Web Services
Scale
Four data-center shells
Investment
Observed hiring
65 employer openings in this market
Verified Oct 14, 2026View project →
Operating + constructionNew Carlisle, Indiana

AWS New Carlisle (St. Joseph County)

Amazon announced its St. Joseph County campus in April 2024 and held a ceremonial groundbreaking that September. Indiana's environmental agency issued an air permit for the first site on Larrison Boulevard in January 2025, and Amazon reported in October 2025 that the county's data centers are part of its operating Project Rainier cluster. No primary source names the campus's builders.

Developer
Amazon Web Services
Scale
Investment
$11B announced in 2024 for data centers in St. Joseph County
Observed hiring
20 employer openings in this market
Verified Oct 14, 2026View project →
ApprovedWest of Boardman, Oregon

AWS Tower Road East (Morrow County)

Morrow County's planning commission approved this Amazon Data Services campus west of Boardman by a 5-2 vote on March 31, 2026, according to its draft minutes. The plan includes four data-center buildings, a water building and an on-site substation that Umatilla Electric Cooperative would own and operate. Construction is not confirmed.

Developer
Amazon Web Services
Scale
Four buildings, about 816,000 sq ft
Investment
Observed hiring
65 employer openings in this market
Verified Oct 14, 2026View project →
Under constructionConesville, Ohio

Aligned CMH-02 (Coshocton County)

Aligned announced a 197-acre campus beside the former AEP Conesville power plant in July 2025, with a customer signed for the first building, and has published groundbreaking highlights. Initial capacity in mid-2026 is an Aligned target that no source yet confirms. The Coshocton County Port Authority secured state funding for the industrial park's water, sewer and roads.

Developer
Aligned Data Centers
Scale
At least three buildings planned
Investment
Multi-billion-dollar phased investment (Aligned); over $2 billion (state representative)
Observed hiring
8 employer openings in this market
Verified Oct 14, 2026View project →
OperatingWest Jordan, Utah

Aligned Salt Lake (West Jordan)

Aligned operates three West Jordan buildings: SLC-02 was announced complete in March 2021 and SLC-03 in October 2024. No contractor or design firm is named for any of them in Aligned's releases. A separate SLC-04 site in West Valley City is not part of this record.

Developer
Aligned Data Centers
Scale
Three buildings, 34–80 MW each
Investment
Observed hiring
3 employer openings in this market
Verified Oct 14, 2026View project →
In developmentNear Castroville, Medina County, Texas

CyrusOne Medina County

CyrusOne is developing a multi-phase campus west of San Antonio on US-90, under a Medina County tax-abatement agreement effective November 3, 2025. Its first building, SAT14A, was registered with the state in July 2026 as a 460,000-square-foot, one-story building designed by Corgan, with an estimated completion of June 1, 2027.

Developer
CyrusOne
Scale
Investment
$4B to $6B expected across multiple phases (CyrusOne)
Observed hiring
7 employer openings in this market
Verified Oct 14, 2026View project →
OperatingSan Antonio, Texas

CyrusOne San Antonio SAT5–SAT6

CyrusOne operates SAT5 and SAT6 at the Texas Research Park. Rogers-O'Brien built SAT V's third phase, TDIndustries installed its mechanical systems (completed in 2021) and Corgan designed the building. Later SAT VI building and data-hall fit-outs were filed with the state; their estimated completion dates have passed without confirmation.

Developer
CyrusOne / Rogers-O'Brien Construction / TDIndustries / Corgan
Scale
33 MW IT capacity
Investment
Observed hiring
7 employer openings in this market
Verified Oct 14, 2026View project →
Operating + expansionEagle Mountain, Utah

Meta Eagle Mountain

Meta reported its Eagle Mountain data center serving traffic on July 14, 2021, and announced a further expansion on September 14, 2026 without a completion date. Rocky Mountain Power is working with Meta on new solar supply. A builder for the expansion is not named in Meta's announcements.

Developer
Meta
Scale
Investment
More than $3B in Utah including the 2026 expansion (Meta)
Observed hiring
Project activity only
Verified Oct 14, 2026View project →
OperatingGallatin, Tennessee

Meta Gallatin

Meta broke ground in Gallatin in August 2020, and DPR's project team topped out the first phase, two buildings of nearly one million square feet, by January 2022. Meta reported the campus serving traffic on November 14, 2024. Full build-out is a Meta target; current construction is not confirmed by a primary source.

Developer
Meta
Scale
About 982,000 sq ft
Investment
$800M announced in 2020; more than $1.5B in Tennessee once fully built out (Meta target)
Observed hiring
Project activity only
Verified Oct 14, 2026View project →
Under constructionEagle Mountain, Utah

QTS Eagle Mountain (SLC1)

QTS is building a five-building first phase on about 193 acres in Eagle Mountain. Construction restarted in 2025 after a delay for energy infrastructure, and QTS and Layton Construction marked the topping-out of the third building on April 17, 2026. QTS targets three buildings first and the other two over the following years.

Developer
QTS Data Centers
Scale
Five-building first phase
Investment
$6B for the first phase (QTS)
Observed hiring
6 employer openings in this market
Verified Oct 14, 2026View project →
Under constructionYork County, South Carolina

QTS York County

QTS is building its first South Carolina campus in York County. Gilbane, the builder, reported the steel topping-out of the first phase-one building on June 30, 2026; QTS says no building is complete or operating yet. Phase one is four buildings, and phase two is planned to start in early 2027.

Developer
QTS Data Centers
Scale
Nine buildings planned
Investment
$8B planned for the approved campus (QTS); $1B at the 2023 announcement
Observed hiring
8 employer openings in this market
Verified Oct 14, 2026View project →
In developmentSan Antonio, Texas

Vantage San Antonio (Rogers Road)

Texas state filings describe a Vantage campus at 5207 Rogers Road: TX22, a new two-story data center designed by Corgan, was registered with an estimated start in October 2025 and completion by June 15, 2027. Construction progress is not confirmed by a primary source.

Developer
Vantage Data Centers
Scale
Investment
Observed hiring
2 employer openings in this market
Verified Oct 14, 2026View project →
Operating + constructionSan Antonio, Texas

Vantage San Antonio TX1

Texas state filings by Vantage describe its TX1 campus on Omicron Drive: TX11, a two-story 32 MW building designed by Sheehan Nagle Hartray Architects, shows its state inspection complete, and TX12, a two-story building designed by Jacobs, was filed with an estimated completion of August 31, 2027. Vantage has not published its own announcement for this campus.

Developer
Vantage Data Centers
Scale
32 MW TX11; up to 96 MW TX12
Investment
Observed hiring
2 employer openings in this market
Verified Oct 14, 2026View project →
Under constructionShippingport, Pennsylvania

Project Phoenix

Aligned has broken ground on a three-facility campus in Shippingport, Pennsylvania. The development plans dedicated onsite power; the company estimates 3,000 construction jobs and 640 ongoing campus roles, not current vacancies.

Developer
Aligned Data Centers
Scale
2 GW planned campus
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
Under constructionDenver, Colorado

CoreSite Denver DE3

DPR documents core-and-shell construction and an 18 MW initial fit-out. CoreSite reports generator testing and commissioning for June 2026. Its community page targets June operations while its market page says end-2026; these conflicting targets do not confirm an opening.

Developer
CoreSite
Scale
18 MW initial phase
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
Under constructionAnkeny, Iowa

Edged Des Moines

Edged's Ankeny data center topped out in August 2025. Its announced service target is the end of 2026; this profile does not treat that future target as delivered capacity.

Developer
Edged US
Scale
13 MW planned critical IT capacity
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
AnnouncedIrving, Texas

Edged Irving second facility

Edged announced a second Irving facility in January 2026 after city approval. Its Q2 2026 groundbreaking date remains an unconfirmed target. The first facility opened in January 2025; that opening does not apply to the second building.

Developer
Edged US
Scale
24 MW planned critical capacity
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
OperatingFort Worth, Texas

Meta Fort Worth

DPR documents phased construction beginning in 2015, first operations in 2017 and campus completion in 2023. This is an operating-campus delivery history, not a newly awarded construction package.

Developer
Meta
Scale
Five-building campus in DPR delivery account
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
OperatingSandston, Virginia

Meta Henrico

Meta reported Henrico serving traffic in August 2020. DPR documents the multi-phase five-building campus in White Oak Technology Park. This operating history does not establish a new construction award or completion of every later phase.

Developer
Meta
Scale
Five-building campus described by DPR
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
AnnouncedRosemount, Minnesota

Meta Rosemount

Meta announced its Rosemount campus in March 2024 and directed construction inquiries to Mortenson. The announcement does not establish a current completion date or an operational handover; its projected workforce is not a count of open jobs.

Developer
Meta
Scale
715,000-square-foot announced campus
Investment
Observed hiring
2 employer openings in this market
Verified Sep 26, 2026View project →
Under constructionCedar Rapids, Iowa

QTS Cedar Rapids

QTS is building a 612-acre campus planned for up to seven data center buildings in the Big Cedar Industrial Center.

Developer
QTS Data Centers
Scale
Investment
$10B planned investment
Observed hiring
12 employer openings in this market
Verified Sep 26, 2026View project →
OperatingHillsboro, Oregon

QTS Hillsboro 1

A 25-acre Portland-area campus supporting large-scale deployments, with redundant feeds and an expandable adjacent substation. The profile describes an operating site rather than a new groundbreaking.

Developer
QTS Data Centers
Scale
20 MW+ critical power capacity
Investment
Observed hiring
2 employer openings in this market
Verified Sep 26, 2026View project →
Phased developmentNew Albany, Ohio

Vantage New Albany OH1

A 70-acre campus planned for three 64 MW buildings. The developer's published schedule describes phased deliveries through 2028; individual handovers require subsequent confirmation.

Developer
Vantage Data Centers
Scale
192 MW planned critical IT load
Investment
Observed hiring
1 employer openings in this market
Verified Sep 26, 2026View project →
In developmentSanta Clara, California

Vantage Santa Clara CA3

A four-story data center planned on roughly eight acres near Vantage's existing Santa Clara campuses, with more than 486,000 square feet of space.

Developer
Vantage Data Centers
Scale
64 MW planned critical IT load
Investment
Observed hiring
4 employer openings in this market
Verified Sep 26, 2026View project →
Site preparationAbilene, Texas

Crusoe Microsoft Abilene

A two-building AI factory campus with dedicated onsite generation, under development adjacent to Crusoe's existing Abilene infrastructure.

Developer
Crusoe
Scale
900 MW
Investment
Observed hiring
3 employer openings in this market
Verified Sep 26, 2026View project →
OperatingMesa, Arizona

Meta Mesa

Meta reported that its Mesa data center began serving traffic in January 2025. DPR describes a five-building campus and identifies its design partners. The operating announcement does not confirm completion of every building or a new construction award.

Developer
Meta
Scale
Five-building campus described by DPR
Investment
Observed hiring
5 employer openings in this market
Verified Sep 26, 2026View project →
Operating + expansionAbilene, Texas

Stargate Abilene

The first phase is operating while the multi-building campus continues to expand for high-density AI workloads.

Developer
Crusoe / Lancium
Scale
1.2 GW planned
Investment
Eight-building campus
Observed hiring
3 employer openings in this market
Verified Sep 26, 2026View project →
Campus developmentAshburn, Virginia

Vantage Ashburn VA3

Vantage's third Northern Virginia campus is designed for seven buildings on 134 acres, with about 2.3 million square feet of space.

Developer
Vantage Data Centers
Scale
288 MW planned critical IT load
Investment
Observed hiring
3 employer openings in this market
Verified Sep 26, 2026View project →
Campus developmentGoodyear, Arizona

Vantage Phoenix AZ1

A 50-acre, five-building campus designed for more than one million square feet of data-center space. The published capacity describes the full campus development.

Developer
Vantage Data Centers
Scale
176 MW planned critical IT load
Investment
Observed hiring
Project activity only
Verified Sep 26, 2026View project →
ConstructionRichland Parish, Louisiana

Hyperion

Turner's July 2026 update describes an expanded Richland Parish campus approaching ten million square feet and 5 GW of IT capacity. The contractor projects about 7,500 workers at peak construction; these are forecast project workers, not current advertised openings.

Developer
Meta
Scale
5 GW planned IT capacity
Investment
More than $50B expanded project investment
Observed hiring
3 employer openings in this market
Verified Sep 10, 2026View project →
Operating + expansionGreater Memphis, Tennessee / Mississippi

Colossus

An operating AI supercomputer campus with continued compute and power-infrastructure expansion across the Greater Memphis area.

Developer
SpaceXAI / Memphis Light, Gas and Water / Tennessee Valley Authority
Scale
Roadmap toward 1M GPUs
Investment
Permanent 1.2 GW power build underway
Observed hiring
Project activity only
Verified Sep 8, 2026View project →
Under constructionSterling, Virginia

EdgeCore Ashburn AS01 / AS02

Two fully leased hyperscale facilities are being developed across 685,000 square feet. Initial occupancy is scheduled separately for AS01 and AS02; the financing covers both buildings.

Developer
EdgeCore Digital Infrastructure
Scale
114 MW combined critical load
Investment
$1.5B construction financing
Observed hiring
28 employer openings in this market
Verified Sep 8, 2026View project →
Under constructionWest Memphis, Arkansas

Google West Memphis

Google is constructing its first Arkansas data center campus, including offices and a substation, in West Memphis. The statewide investment also covers other infrastructure and programs, so it is not presented as a site-only construction budget. A campus handover date and trade awards remain unconfirmed.

Developer
Google
Scale
More than 1,000-acre planned campus
Investment
Part of Google's $4B Arkansas investment through 2027
Observed hiring
3 employer openings in this market
Verified Sep 8, 2026View project →
Under constructionLebanon, Indiana

Meta Lebanon

Meta's approximately four-million-square-foot campus has broken ground in Lebanon. Turner and Mortenson identify construction partnerships and an expected peak workforce of about 4,000; this is a project forecast, not a count of open jobs.

Developer
Meta
Scale
1 GW planned campus
Investment
$10B announced investment
Observed hiring
11 employer openings in this market
Verified Sep 8, 2026View project →
Under constructionTulsa, Oklahoma

Meta Tulsa

Meta broke ground on its first Oklahoma data center in April 2026 with Fortis Construction as general contractor. The campus includes local infrastructure improvements and is expected to employ more than 1,000 construction workers at peak.

Developer
Meta
Scale
More than 2 million square feet planned
Investment
More than $1B announced campus investment
Observed hiring
Project activity only
Verified Sep 8, 2026View project →
Vertical constructionClay, New York

Micron Clay / Central New York

Micron reported its first concrete pour in July 2026, following January groundbreaking. Bechtel is the first fab's EPC partner, Jacobs leads architectural and engineering design, and Gilbane handles preconstruction and site infrastructure. The company-wide investment plan is not a site-level budget.

Developer
Micron Technology
Scale
First fab within a planned four-fab campus
Investment
Observed hiring
5 employer openings in this market
Verified Sep 8, 2026View project →
Under constructionIndependence, Missouri

Nebius Independence AI factory

Nebius broke ground on a roughly 400-acre campus in May 2026. March's Chapter 100 incentive approval and the subsequent groundbreaking are separate milestones; the incentive decision is not a building permit.

Developer
Nebius
Scale
Up to 1.2 GW planned campus capacity
Investment
Observed hiring
2 employer openings in this market
Verified Sep 8, 2026View project →
Operating + expansionPhoenix, Arizona

TSMC Arizona

The first fab entered volume production in late 2024. TSMC reports ongoing development of additional logic fabs and advanced packaging, including initial construction on a fourth fab and first packaging fab in early 2026.

Developer
TSMC
Scale
Multi-fab manufacturing and advanced packaging campus
Investment
Observed hiring
52 employer openings in this market
Verified Sep 8, 2026View project →
Under constructionShackelford County, Texas

Vantage Frontier

A 1,200-acre AI campus planned for ten buildings and 3.7 million square feet. The developer targets first delivery in the second half of 2026 and specifies liquid cooling for high-density GPU workloads.

Developer
Vantage Data Centers
Scale
1.4 GW planned critical IT load
Investment
More than $25B announced campus investment
Observed hiring
13 employer openings in this market
Verified Sep 8, 2026View project →
Under constructionAbernathy / Hale County, Texas

Aligned Project Caprock

Aligned's six-facility campus outside Abernathy is planned across 313 acres. The first building, LBB-01, targets service in Q1 2027; the full campus is a multi-year development.

Developer
Aligned Data Centers
Scale
540 MW planned campus
Investment
$5B expected regional investment
Observed hiring
2 employer openings in this market
Verified Sep 7, 2026View project →
Under constructionBoyce / Rapides Parish, Louisiana

Applied Digital Delta Forge 1

Applied Digital is developing two data center buildings in Central Louisiana. Initial operations are targeted for mid-2027; campus-wide capacity is not delivered capacity.

Developer
Applied Digital
Scale
300 MW planned critical IT load
Investment
$3.6B announced campus investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Operating + constructionEllendale, North Dakota

Applied Digital Polaris Forge 1

Applied Digital delivered another 75 MW at its Ellendale AI campus in June 2026, with additional buildings still under construction. CoreWeave is the contracted customer. The adjacent legacy bitcoin-hosting capacity is separate from this AI campus rating.

Developer
Applied Digital
Scale
400 MW contracted critical IT load; 175 MW live as reported July 2026
Investment
Observed hiring
1 employer openings in this market
Verified Sep 7, 2026View project →
Under constructionHarwood, North Dakota

Applied Digital Polaris Forge 2

Applied Digital's Harwood campus remains under construction in its July 2026 update. The financing is allocated to 200 MW of critical IT load; it is not an operating-capacity figure or a total campus construction budget. A named general contractor is not confirmed in this coverage.

Developer
Applied Digital
Scale
200 MW financed critical IT load
Investment
$2.15B senior secured notes for development
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionColorado City, Texas

Cipher Barber Lake

Cipher reported construction and fit-out progressing at Barber Lake in August 2026, including initial tenant access. Gross power capacity is not live critical IT load; remaining delivery is phased.

Developer
Cipher Mining
Scale
300 MW gross campus power capacity
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Operating + constructionWink, Texas

Cipher Black Pearl

The Black Pearl campus combines existing operations and HPC construction. Cipher's August update reports initial HPC delivery alongside remaining mechanical, electrical and plumbing work and second-phase structural activity.

Developer
Cipher Mining
Scale
300 MW gross campus power capacity
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Site preparationAndrews County, Texas

Cipher Stingray

Stingray is in site preparation for a contracted hyperscale development. Lease commencement targets are phased during April and May 2027; these contractual dates are not a claim of completed commissioning.

Developer
Cipher Mining
Scale
70 MW planned critical IT load / 100 MW gross power
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
In developmentLouisa County, Virginia

EdgeCore Louisa County

EdgeCore's 697-acre campus is planned for phased development totaling more than 3.1 million square feet. The full-campus plan is not operating capacity, and named construction-package awards are not established in this coverage.

Developer
EdgeCore Digital Infrastructure
Scale
More than 1.1 GW planned critical IT load across six data centers
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionAtlanta, Georgia

Edged Atlanta third building

The third building at Edged's Atlanta campus topped out in April 2026, with operations targeted for early 2027. Construction, design, cooling and power partners are identified for this building rather than assumed across the entire campus.

Developer
Edged US
Scale
42 MW planned critical IT capacity
Investment
Observed hiring
21 employer openings in this market
Verified Sep 7, 2026View project →
Under constructionAurora, Illinois

Edged Chicago second building

Edged's second Chicago-campus building topped out in June 2026 and targets Q2 2027 service. It is distinct from the first building that opened in 2025.

Developer
Edged US
Scale
72 MW planned critical IT capacity
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionAbernathy / Hale County, Texas

Fluidstack / TeraWulf Abernathy

This campus is distinct from Aligned's Project Caprock in the same area. TeraWulf announced an agreement to sell its 50.1% joint-venture interest to Fluidstack; the August update had not reported the transaction closed.

Developer
TeraWulf / Fluidstack
Scale
168 MW planned critical IT load
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionGray and Roberts Counties, Texas

Google Meitner Energy Center

Google and Intersect Power broke ground on an integrated data center and energy development in June 2026. The energy developer's role does not establish a general-contractor or trade-package award.

Developer
Google / Intersect Power
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionWilbarger County, Texas

Google Wilbarger County

Google broke ground on its Wilbarger County data center in February 2026. AES is associated with the power infrastructure; corporate energy purchases are not attributed as campus IT capacity or construction spending.

Developer
Google
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionChildress, Texas

IREN Childress Horizon

IREN's Microsoft AI-cloud deployment is planned across four Horizon phases during 2026. The service contract value is not a campus capital budget, and the existing site's power capacity is distinct from the contracted IT deployment.

Developer
IREN
Scale
200 MW IT capacity for Microsoft within a 750 MW power campus
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionSweetwater, Texas

IREN Sweetwater

Sweetwater combines 1,400 MW and 600 MW power-enabled development sites. Substation delivery is phased across 2026 and 2027. Power capacity is not commissioned IT load or currently advertised labor demand.

Developer
IREN
Scale
2 GW planned power capacity across two sites
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionBeaver Dam, Wisconsin

Meta Beaver Dam

Meta is developing an AI-focused campus with Mortenson as general contractor and Alliant Energy coordinating power requirements. The city's fact sheet targets the initial data center for 2027. A possible second phase is not treated as an awarded construction package.

Developer
Meta
Scale
More than 700,000 square feet planned
Investment
$1B announced campus investment
Observed hiring
1 employer openings in this market
Verified Sep 7, 2026View project →
Under constructionEl Paso, Texas

Meta El Paso

Construction is underway on Meta's El Paso campus, with initial capacity targeted for 2028 and a projected peak construction workforce of more than 4,000. Meta announced a BlackRock-backed development venture in July 2026, subject to closing.

Developer
Meta
Scale
1 GW planned compute capacity
Investment
Approximately $14B proposed venture development cost
Observed hiring
6 employer openings in this market
Verified Sep 7, 2026View project →
Construction + expansionMontgomery, Alabama

Meta Montgomery

Meta expanded the original Montgomery campus plan with two additional buildings in September 2025. Hensel Phelps documents its original construction award and a mass-timber administrative facility. Its end-2026 completion target covers the original contract, not a confirmed handover of the expanded campus.

Developer
Meta
Scale
Nearly 1.3 million square feet planned
Investment
More than $1.5B expanded campus investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionBoise, Idaho

Micron Boise ID1 / ID2

Micron is building two Idaho memory fabs alongside its existing R&D operations. Its July update targets initial output in mid-2027 for ID1 and late 2028 for ID2. Kiewit identifies construction-management work on the Boise expansion.

Developer
Micron Technology
Scale
Two planned leading-edge DRAM fabs
Investment
Observed hiring
38 employer openings in this market
Verified Sep 7, 2026View project →
Under constructionMaiden, North Carolina

Microsoft Boyd Farms

Microsoft's May 2026 update describes continuing construction at Boyd Farms. Morgan Corp. was named for initial site preparation; that relationship is not an award for all subsequent building work.

Developer
Microsoft
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Site preparationHeath, Ohio

Microsoft Heath

Microsoft's July 2026 update identifies Ames Construction on site preparation. The anticipated end-of-2026 completion applies to site preparation, not delivery of an operating data center.

Developer
Microsoft
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Site preparationHebron, Ohio

Microsoft Hebron

Ames Construction is conducting site preparation for Microsoft's Hebron development. The July update targets completion of that preparation by the end of 2026; a vertical-construction delivery date is not specified.

Developer
Microsoft
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionHickory / Newton, North Carolina

Microsoft Hickory / Stover

The May 2026 update describes utilities and foundations, with Clayco leading the current construction phase. Ames handled earlier excavation. The announced late-June steel-work target is retained as a target, not a verified completed milestone.

Developer
Microsoft
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Operating + constructionMount Pleasant, Wisconsin

Microsoft Mount Pleasant / Fairwater

Microsoft's first facility is operating. The adjacent second facility remains under construction, with foundations, structural steel and underground utilities underway and completion targeted for 2028. Separate early earthwork supports further development; it is not a third operating facility.

Developer
Microsoft
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionVineland, New Jersey

Nebius / DataOne Vineland

DataOne is developing and operating the campus for Nebius' GPU infrastructure, with Northeast Precast leading construction and Bloom Energy supplying fuel cells. The project targets operations in 2027. The January PILOT ordinance is a tax arrangement, not a building permit.

Developer
DataOne
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Operating campus / expansion capacityAtlanta, Georgia

QTS Atlanta 1

A 99-acre campus with direct carrier fiber access and an expandable substation plan supporting staged campus development.

Developer
QTS Data Centers
Scale
278 MW+ critical campus capacity
Investment
Observed hiring
9 employer openings in this market
Verified Sep 7, 2026View project →
Operating + expansion leasingChicago, Illinois

QTS Chicago 1

A 30-acre campus near downtown Chicago. QTS is marketing pre-leasing for its second building; this does not by itself establish a construction start or delivery date.

Developer
QTS Data Centers
Scale
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Operating campus / expansion capacityAurora, Colorado

QTS Denver 1

QTS's 65-acre Aurora campus includes owned land for further growth. Its published 160 MW-plus figure is planned campus capacity, not a measure of current construction jobs.

Developer
QTS Data Centers
Scale
160 MW+ planned critical power
Investment
Observed hiring
1 employer openings in this market
Verified Sep 7, 2026View project →
Operating campus / expansion capacityFort Worth, Texas

QTS Fort Worth 1

A 52-acre campus with twelve adjacent acres identified for future expansion. QTS distinguishes critical capacity from the larger gross campus power potential.

Developer
QTS Data Centers
Scale
70 MW+ critical; 200 MW gross planned potential
Investment
Observed hiring
12 employer openings in this market
Verified Sep 7, 2026View project →
Operating campus / expansion capacityIrving, Texas

QTS Irving 1

A 56-acre master-planned campus with six facilities and campus fiber pathways connecting current and future buildings.

Developer
QTS Data Centers
Scale
165 MW+ critical campus capacity
Investment
Observed hiring
12 employer openings in this market
Verified Sep 7, 2026View project →
Operating campus / expansion capacitySandston, Virginia

QTS Richmond 1

A 207-acre campus with a six-facility master plan and 2.3 million square feet of current space. QTS identifies multiple building addresses within the same campus.

Developer
QTS Data Centers
Scale
238 MW campus critical power
Investment
Observed hiring
1 employer openings in this market
Verified Sep 7, 2026View project →
Construction and manufacturing preparationTaylor, Texas

Samsung Taylor

Samsung is developing a logic-chip manufacturing facility in Taylor alongside its established Austin operations. Samsung E&C America is the lead general contractor. The original Taylor investment plan covers buildings, property improvements, machinery and equipment.

Developer
Samsung Austin Semiconductor
Scale
Investment
At least $17B original Taylor buildout plan
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionSaline Township, Michigan

Stargate Michigan / Saline

Related Digital is developing a Saline Township campus for Oracle and OpenAI. Walbridge confirmed active construction in May 2026 under a project labor agreement covering more than 2,500 union tradespeople and apprentices; that figure is not a count of advertised vacancies.

Developer
Related Digital
Scale
Gigawatt-scale planned campus
Investment
$16B announced campus investment
Observed hiring
14 employer openings in this market
Verified Sep 7, 2026View project →
Phased developmentHawesville / Hancock County, Kentucky

TeraWulf Justified Data

TeraWulf's phased campus has an Anthropic lease and an approved electric-service agreement. Initial delivery targets the second half of 2027, with full contracted delivery in early 2028. Lease revenue is not a construction budget.

Developer
TeraWulf
Scale
401 MW contracted critical IT load; up to 482 MW electric service
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Operating + constructionBarker / Somerset, New York

TeraWulf Lake Mariner expansion

The operating HPC campus continues its phased expansion. CB4 targets delivery in the second half of 2026 and CB5 in early 2027. These are separate construction and operating capacity figures.

Developer
TeraWulf
Scale
102 MW operating and 336 MW under construction, reported August 2026
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Under constructionPort Washington, Wisconsin

Vantage Lighthouse

A 672-acre AI campus planned for four buildings and 2.5 million square feet. Vantage's campus profile targets completion in 2028.

Developer
Vantage Data Centers
Scale
902 MW planned critical IT load
Investment
Observed hiring
6 employer openings in this market
Verified Sep 7, 2026View project →
OperatingQuincy, Washington

Vantage Quincy WA1

An operating 68-acre campus with three data centers and approximately 775,000 square feet. This is an operations footprint, not a newly announced construction project.

Developer
Vantage Data Centers
Scale
89 MW campus critical IT load
Investment
Observed hiring
Project activity only
Verified Sep 7, 2026View project →
Phased developmentStorey County, Nevada

Vantage Reno NV1

A 137-acre, four-building campus designed for air and liquid cooling. The campus profile identifies a second-quarter 2026 opening target for the first facility, not a confirmed handover.

Developer
Vantage Data Centers
Scale
224 MW planned critical IT load
Investment
Observed hiring
3 employer openings in this market
Verified Sep 7, 2026View project →
In developmentCedar Rapids, Iowa

Google Cedar Rapids

Google is developing a new Cedar Rapids data center campus while expanding Iowa's electrical-workforce pipeline to support the infrastructure buildout.

Developer
Google
Scale
Investment
Part of Google's $7B two-year Iowa investment
Observed hiring
5 employer openings in this market
Verified Sep 1, 2026View project →
Development + constructionSt. Francisville, Louisiana

River Bend

A staged AI data-center campus with a defined construction, commissioning, and operations labor transition.

Developer
Hut 8
Scale
330 MW commercialized; 1 GW potential
Investment
Up to $10B phase-one investment
Observed hiring
1 employer openings in this market
Verified Aug 31, 2026View project →
Operating + expansionMuskogee, Oklahoma

Core Scientific Muskogee

Core Scientific is expanding its Muskogee campus using 440 MW of acquired grid-connected power, with the next approximately 82 MW targeted for customer delivery beginning in the second half of 2027.

Developer
Core Scientific
Scale
1.5 GW gross target
Investment
$444M power acquisition
Observed hiring
3 employer openings in this market
Verified Aug 14, 2026View project →
PlannedPecos County, Texas

Amazon Pecos County

A planned data center campus expected to use new onsite generation initially and transition to grid-connected service as interconnection becomes available.

Developer
Amazon Web Services
Scale
Investment
Observed hiring
Project activity only
Verified Aug 10, 2026View project →
Under constructionNueces County, Texas

Beacon Point

A fully contracted AI data center campus under construction with two 352 MW leases and initial energization scheduled for the first quarter of 2027.

Developer
Hut 8
Scale
704 MW contracted IT; 1 GW utility
Investment
$19.6B base-term campus value
Observed hiring
Project activity only
Verified Jul 20, 2026View project →
Construction startingChildress, Texas

Crusoe Childress

A 270-acre AI data center campus developed by Crusoe and Lancium, with construction scheduled to begin in the third quarter of 2026.

Developer
Crusoe / Lancium
Scale
1 GW
Investment
Observed hiring
5 employer openings in this market
Verified Jul 15, 2026View project →