PROJECT Under construction

Cipher Barber Lake

Cipher reported construction and fit-out progressing at Barber Lake in August 2026, including initial tenant access. Gross power capacity is not live critical IT load; remaining delivery is phased.

Colorado City, Texas300 MW gross campus power capacityCipher Mining
64-day coverage window Coverage

Project facts

Developer / owner
Cipher Mining
Industry
Data centers
Capacity marker
300 MW gross campus power capacity
Record status
Verified Sep 7, 2026
View project source ↗

Workforce outlook

No linked openings yet; tracked from public milestones.

Openings are linked by project employer and labor market, so a posting may also serve other sites in the market. See hiring in Colorado City, Texas →

DevelopmentConstructionCommissioningOperations

Project participants

Customer
Fluidstack · Source ↗

HPC tenant named in the construction update.

Milestones and targets

August 4, 2026 Reported
Construction and tenant-access update · Source ↗

Targets reflect published schedules and are not confirmed completions.

Construction progress

Running
Not yet running · Epoch estimate, Jul 2026
Planned
About 207 MW in 1 building by Apr 2027 · Epoch projection
Jul 30, 2026 Seen
Building 1's shell is complete with rooftop units installed, most chillers are in place and most of its 120 backup generators are set. Not yet energized.
Nov 29, 2025 Seen
Foundations for Building 1 are visible.
Sep 18, 2025 Seen
Site grading and civil works begin.
Epoch site page ↗