PROJECT Operating + expansion

Colossus

An operating AI supercomputer campus with continued compute and power-infrastructure expansion across the Greater Memphis area.

Greater Memphis, Tennessee / MississippiRoadmap toward 1M GPUsSpaceXAI / Memphis Light, Gas and Water / Tennessee Valley Authority
Updated Oct 18 · 2:14 PM UTC 46-day coverage window Coverage

Project facts

Developer / owner
SpaceXAI / Memphis Light, Gas and Water / Tennessee Valley Authority
Industry
Data centers
Capacity marker
Roadmap toward 1M GPUs
Capital marker
Permanent 1.2 GW power build underway
Record status
Verified Sep 8, 2026
View project source ↗

Workforce outlook

No linked openings yet; tracked from public milestones.

Openings are linked by project employer and labor market, so a posting may also serve other sites in the market. See hiring in Greater Memphis, Tennessee / Mississippi →

DevelopmentConstructionCommissioningOperations

Project participants

Utility
Memphis Light, Gas and Water · Source ↗

Utility coordination identified for Memphis facilities; not assigned as the builder of the separate Southaven permanent power plant.

Utility
Tennessee Valley Authority · Source ↗

Power-system coordination identified for Memphis facilities; not a construction-contract award.

Milestones and targets

July 30, 2026 Reported
Southaven temporary-power transition agreement reported by operator · Source ↗
July 2027 Target
Southaven temporary-turbine removal deadline announced by operator · Source ↗

Targets reflect published schedules and are not confirmed completions.