PROJECT TERMINAL Under construction
CoreSite Denver DE3
DPR documents core-and-shell construction and an 18 MW initial fit-out. CoreSite reports generator testing and commissioning for June 2026. Its community page targets June operations while its market page says end-2026; these conflicting targets do not confirm an opening.
Current project facts.
- Developer / owner
- CoreSite
- Market
- Denver, Colorado
- Site
- 4900 Race Street, Denver, CO 80216
- Industry
- Data centers
- Capacity marker
- 18 MW initial phase
- Capital marker
- Record status
- Verified Sep 26, 2026
Project activity only
Follow current role activity around the project from development and construction through commissioning and operations.
Openings are matched by project employer and labor market. Individual postings may serve other sites in the same market.
Project participants
- Construction Partner
- DPR Construction · Source ↗
Initial core and shell plus 18 MW tenant improvements across three computer rooms; not all future campus buildings.
Milestones and delivery targets.
- June 2026 · Reported
- Generator testing / commissioning update · Source ↗
- June 2026 · Target
- Operations target on community page (conflicts with market page) · Source ↗
- End of 2026 · Target
- Opening target on market page (conflicts with community page) · Source ↗
Targets reflect published schedules and are not confirmed completions.
HIRING LINKED MARKET
Current openings.
No current openings matched to this project or market.
New roles will appear here as nearby hiring changes.