PROJECT Operating + expansion

Meta Eagle Mountain

Meta reported its Eagle Mountain data center serving traffic on July 14, 2021, and announced a further expansion on September 14, 2026 without a completion date. Rocky Mountain Power is working with Meta on new solar supply. A builder for the expansion is not named in Meta's announcements.

Eagle Mountain, UtahMeta
Updated Oct 14 · 8:45 PM UTC 43-day coverage window Coverage

Project facts

Developer / owner
Meta
Industry
Data centers
Capital marker
More than $3B in Utah including the 2026 expansion (Meta)
Record status
Verified Oct 14, 2026
View project source ↗

Workforce outlook

No linked openings yet; tracked from public milestones.

Openings are linked by project employer and labor market, so a posting may also serve other sites in the market. See hiring in Eagle Mountain, Utah →

DevelopmentConstructionCommissioningOperations

Project participants

Owner
Meta · Source ↗

Owner and operator of the Eagle Mountain campus.

Utility
Rocky Mountain Power · Source ↗

Working with Meta to add new solar supply for its Utah operations.

Milestones and targets

July 14, 2021 Reported
Campus serving traffic · Source ↗
September 14, 2026 Reported
Further expansion announced · Source ↗

Targets reflect published schedules and are not confirmed completions.