PROJECT Operating
Meta Gallatin
Meta broke ground in Gallatin in August 2020, and DPR's project team topped out the first phase, two buildings of nearly one million square feet, by January 2022. Meta reported the campus serving traffic on November 14, 2024. Full build-out is a Meta target; current construction is not confirmed by a primary source.
Project facts
- Developer / owner
- Meta
- Market
- Gallatin, Tennessee
- Industry
- Data centers
- Capacity marker
- About 982,000 sq ft
- Capital marker
- $800M announced in 2020; more than $1.5B in Tennessee once fully built out (Meta target)
- Record status
- Verified Oct 14, 2026
Workforce outlook
No linked openings yet; tracked from public milestones.
Openings are linked by project employer and labor market, so a posting may also serve other sites in the market. See hiring in Gallatin, Tennessee →
Project participants
- Construction Partner
- DPR Construction · Source ↗
Project team that topped out the first phase (two buildings, nearly one million square feet). Contractors for later buildings are not specified.
- Utility
- Tennessee Valley Authority · Source ↗
Worked with Meta to plan the campus's energy needs.
Milestones and targets
- August 12, 2020 Reported
- Groundbreaking · Source ↗
- January 2022 Reported
- First-phase topping-out reported by DPR · Source ↗
- November 14, 2024 Reported
- Campus serving traffic · Source ↗
Targets reflect published schedules and are not confirmed completions.