PROJECT Under construction

Nebius / DataOne Vineland

DataOne is developing and operating the campus for Nebius' GPU infrastructure, with Northeast Precast leading construction and Bloom Energy supplying fuel cells. The project targets operations in 2027. The January PILOT ordinance is a tax arrangement, not a building permit.

Vineland, New JerseyDataOne
64-day coverage window Coverage

Project facts

Developer / owner
DataOne
Industry
Data centers
Record status
Verified Sep 7, 2026
View project source ↗

Workforce outlook

No linked openings yet; tracked from public milestones.

Openings are linked by project employer and labor market, so a posting may also serve other sites in the market. See hiring in Vineland, New Jersey →

DevelopmentConstructionCommissioningOperations

Project participants

Owner
DataOne · Source ↗

Campus developer and operator.

Customer
Nebius · Source ↗

GPU infrastructure tenant.

Construction Partner
Northeast Precast · Source ↗

Named construction lead.

Equipment
Bloom Energy · Source ↗

Fuel-cell power equipment.

Milestones and targets

January 2026 Reported
PILOT ordinance · Source ↗
2027 Target
Initial operations · Source ↗

Targets reflect published schedules and are not confirmed completions.

Construction progress

Running
About 50 MW in 1 building · Epoch estimate, Jul 2026
Jul 12, 2026 Seen
The building shell is closer to completion, and more chillers have arrived, though they don't yet appear connected.
Apr 15, 2026 Seen
About 30 chillers are in place, enough for the first 50 MW phase, which is estimated to have started running early in 2026.
Dec 15, 2025 Seen
The building is still unfinished, with chillers for the second half of the first phase not yet installed.
Epoch site page ↗

Seen: visible in satellite or drone images. Reported: stated by the company or a public agency. Estimate: Epoch AI’s judgment from progress so far. Building numbers are Epoch’s. Summarized from Epoch AI, AI data centers (updated Nov 1, 2026), CC BY 4.0.