A 25-acre Portland-area campus supporting large-scale deployments, with redundant feeds and an expandable adjacent substation. The profile describes an operating site rather than a new groundbreaking.
Hillsboro, Oregon20 MW+ critical power capacityQTS Data Centers
Project facts
- Developer / owner
- QTS Data Centers
- Market
- Hillsboro, Oregon
- Site
- 4951 NE Huffman St, Hillsboro, Oregon
- Industry
- Data centers
- Power
- Diverse transformer feeds, adjacent expandable substation and generators with 48 hours of fuel storage.
- Capacity marker
- 20 MW+ critical power capacity
- Record status
- Verified Sep 26, 2026
Workforce outlook
No linked openings yet; tracked from public milestones.
Openings are linked by project employer and labor market, so a posting may also serve other sites in the market. See hiring in Hillsboro, Oregon →
DevelopmentConstructionCommissioningOperations
Project participants
- Developer
- QTS Data Centers · Source ↗
- Construction Partner
- Fortis Construction · Source ↗
Historical 158,635-square-foot shell and core with one finished data hall and space for three more. This is not an award for all subsequent campus phases.
Milestones and targets
- 2020 Reported
- New Hillsboro facility completion reported in 2020 ESG report · Source ↗
Targets reflect published schedules and are not confirmed completions.