Inventory assessed Sep 26, 2026 · 03:06 UTC. Regional openings are not confirmed assignments to the projects in this brief.

61data-center / fab openings
9hiring employers
47with published pay
2with mobility terms

9 of 9 feeds for employers represented here are current within six hours. Delayed feeds retain their last available inventory. Source freshness →

Explore all Chicago metro openings →

Projects and delivery responsibilities

A partial market roster. Targets remain targets until confirmed; operating campuses provide delivery context, not evidence of a new construction award.

Edged Chicago second building →

Under construction · Data center · Record updated Sep 7, 2026
72 MW planned critical IT capacity

Edged's second Chicago-campus building topped out in June 2026 and targets Q2 2027 service. It is distinct from the first building that opened in 2025.

Who is involved

Milestones

  • Reported · June 4, 2026

    Topping-out announcement Source ↗

  • Target · Q2 2027

    Ready for service Source ↗

Evidence and dates · 1 sources

QTS Chicago 1 →

Operating + expansion leasing · Data center · Record updated Sep 7, 2026

A 30-acre campus near downtown Chicago. QTS is marketing pre-leasing for its second building; this does not by itself establish a construction start or delivery date.

Who is involved

Milestones

No dated milestones are documented.

Evidence and dates · 1 sources