BUILDOUT BRIEFS San Antonio metro

San Antonio metro: projects and hiring

4 sourced project profiles, documented delivery responsibilities and current regional openings.

Sourced project records · evidence dates are listed below · San Antonio metro market →

Hiring in San Antonio metro

Inventory assessed Nov 28, 2026 · 23:19 UTC. Regional openings are not confirmed assignments to the projects in this brief.

47data-center / fab openings
15hiring employers
16with published pay
4with mobility terms

15 of 15 feeds for employers represented here are current within six hours. Delayed feeds retain their last available inventory. Source freshness →

Explore all San Antonio metro openings →

Projects and delivery responsibilities

A partial market roster. Targets remain targets until confirmed; operating campuses provide delivery context, not evidence of a new construction award.

CyrusOne Medina County →

In development · Data center · Record updated Oct 14, 2026

CyrusOne is developing a multi-phase campus west of San Antonio on US-90, under a Medina County tax-abatement agreement effective November 3, 2025. Its first building, SAT14A, was registered with the state in July 2026 as a 460,000-square-foot, one-story building designed by Corgan, with an estimated completion of June 1, 2027.

Who is involved

Milestones

  • Reported · November 3, 2025

    County tax-abatement agreement effective Source ↗

  • Reported · July 16, 2026

    SAT14A building registered with the state Source ↗

  • Target · June 1, 2027

    SAT14A estimated completion Source ↗

Evidence and dates · 3 sources

CyrusOne San Antonio SAT5–SAT6 →

Operating · Data center · Record updated Oct 14, 2026
33 MW IT capacity

CyrusOne operates SAT5 and SAT6 at the Texas Research Park. Rogers-O'Brien built SAT V's third phase, TDIndustries installed its mechanical systems (completed in 2021) and Corgan designed the building. Later SAT VI building and data-hall fit-outs were filed with the state; their estimated completion dates have passed without confirmation.

Who is involved

Milestones

  • Reported · 2021

    SAT V mechanical systems complete Source ↗

Evidence and dates · 4 sources

Vantage San Antonio (Rogers Road) →

In development · Data center · Record updated Oct 14, 2026

Texas state filings describe a Vantage campus at 5207 Rogers Road: TX22, a new two-story data center designed by Corgan, was registered with an estimated start in October 2025 and completion by June 15, 2027. Construction progress is not confirmed by a primary source.

Who is involved

Milestones

  • Target · June 15, 2027

    TX22 estimated completion Source ↗

Evidence and dates · 1 sources

Vantage San Antonio TX1 →

Operating + construction · Data center · Record updated Oct 14, 2026
32 MW TX11; up to 96 MW TX12

Texas state filings by Vantage describe its TX1 campus on Omicron Drive: TX11, a two-story 32 MW building designed by Sheehan Nagle Hartray Architects, shows its state inspection complete, and TX12, a two-story building designed by Jacobs, was filed with an estimated completion of August 31, 2027. Vantage has not published its own announcement for this campus.

Who is involved

Milestones

  • Reported · December 15, 2023

    TX11 building filed with the state Source ↗

  • Target · August 31, 2027

    TX12 estimated completion Source ↗

Evidence and dates · 2 sources