BUILDOUT BRIEFS San Antonio metro

San Antonio metro: projects and hiring

4 sourced project profiles, documented delivery responsibilities and current regional openings.

Sourced project records · evidence dates are listed below · San Antonio metro market →

Hiring in San Antonio metro

Inventory assessed Oct 14, 2026 · 20:51 UTC. Regional openings are not confirmed assignments to the projects in this brief.

25data-center / fab openings
9hiring employers
8with published pay
3with mobility terms

9 of 9 feeds for employers represented here are current within six hours. Delayed feeds retain their last available inventory. Source freshness →

Explore all San Antonio metro openings →

Projects and delivery responsibilities

A partial market roster. Targets remain targets until confirmed; operating campuses provide delivery context, not evidence of a new construction award.

CyrusOne Medina County →

In development · Data center · Record updated Oct 14, 2026

CyrusOne is developing a multi-phase campus west of San Antonio on US-90, under a Medina County tax-abatement agreement effective November 3, 2025. Its first building, SAT14A, was registered with the state in July 2026 as a 460,000-square-foot, one-story building designed by Corgan, with an estimated completion of June 1, 2027.

Who is involved

Milestones

  • Reported · November 3, 2025

    County tax-abatement agreement effective Source ↗

  • Reported · July 16, 2026

    SAT14A building registered with the state Source ↗

  • Target · June 1, 2027

    SAT14A estimated completion Source ↗

Evidence and dates · 3 sources

CyrusOne San Antonio SAT5–SAT6 →

Operating · Data center · Record updated Oct 14, 2026
33 MW IT capacity

CyrusOne operates SAT5 and SAT6 at the Texas Research Park. Rogers-O'Brien built SAT V's third phase, TDIndustries installed its mechanical systems (completed in 2021) and Corgan designed the building. Later SAT VI building and data-hall fit-outs were filed with the state; their estimated completion dates have passed without confirmation.

Who is involved

Milestones

  • Reported · 2021

    SAT V mechanical systems complete Source ↗

Evidence and dates · 4 sources

Vantage San Antonio (Rogers Road) →

In development · Data center · Record updated Oct 14, 2026

Texas state filings describe a Vantage campus at 5207 Rogers Road: TX22, a new two-story data center designed by Corgan, was registered with an estimated start in October 2025 and completion by June 15, 2027. Construction progress is not confirmed by a primary source.

Who is involved

Milestones

  • Target · June 15, 2027

    TX22 estimated completion Source ↗

Evidence and dates · 1 sources

Vantage San Antonio TX1 →

Operating + construction · Data center · Record updated Oct 14, 2026
32 MW TX11; up to 96 MW TX12

Texas state filings by Vantage describe its TX1 campus on Omicron Drive: TX11, a two-story 32 MW building designed by Sheehan Nagle Hartray Architects, shows its state inspection complete, and TX12, a two-story building designed by Jacobs, was filed with an estimated completion of August 31, 2027. Vantage has not published its own announcement for this campus.

Who is involved

Milestones

  • Reported · December 15, 2023

    TX11 building filed with the state Source ↗

  • Target · August 31, 2027

    TX12 estimated completion Source ↗

Evidence and dates · 2 sources

More buildout briefs · Inspect our coverage · Suggest a correction