PROJECT TERMINAL Phased development

TeraWulf Justified Data

TeraWulf's phased campus has an Anthropic lease and an approved electric-service agreement. Initial delivery targets the second half of 2027, with full contracted delivery in early 2028. Lease revenue is not a construction budget.

Hawesville / Hancock County, Kentucky401 MW contracted critical IT load; up to 482 MW electric serviceTeraWulf
Updated Sep 21 · 1:22 PM UTC 19-day coverage window Coverage
StagePhased developmentCurrent project status
Linked job signals0Current nearby openings
Hiring companies0Within the linked market
Dominant role phaseBuilding baselineCurrent hiring mix
PROJECT PROFILE

Current project facts.

Developer / owner
TeraWulf
Industry
Data centers
Capacity marker
401 MW contracted critical IT load; up to 482 MW electric service
Capital marker
Record status
Verified Sep 7, 2026
View project source ↗
WORKFORCE OUTLOOK

Project activity only

Follow current role activity around the project from development and construction through commissioning and operations.

Openings are matched by project employer and labor market. Individual postings may serve other sites in the same market.

DevelopmentConstructionCommissioningOperations

Project participants

Developer
TeraWulf · Source ↗
Customer
Anthropic · Source ↗

Customer under the announced campus lease.

PROJECT TIMELINE

Milestones and delivery targets.

July 6, 2026 · Reported
Campus lease announced · Source ↗
August 21, 2026 · Reported
Kentucky PSC electric-service agreement approval · Source ↗
H2 2027 · Target
Initial contracted delivery · Source ↗

Targets reflect published schedules and are not confirmed completions.

INTELLIGENCE TAPE LINKED PROJECT

Public milestones and transactions.

Full tape →
Power Agreement

Kentucky PSC Approves 482 MW Power Agreement for TeraWulf’s Justified Data Campus

TeraWulf reports Kentucky approval of an electric-service agreement for its redevelopment of the former Hawesville aluminum site. The agreement assigns project-specific infrastructure and power-delivery costs to TeraWulf and authorizes Big Rivers and Kenergy to implement its terms. Approval does not establish that the campus is energized.

Power agreement approvedIndustrial-site reuseUtility infrastructure
Capacity
482 MW electricity supply

HIRING LINKED MARKET