BUILDOUT BRIEFS Nashville region

Nashville region: projects and hiring

1 sourced project profile, documented delivery responsibilities and current regional openings.

Sourced project records · evidence dates are listed below · Nashville region market →

Hiring in Nashville region

Inventory assessed Oct 14, 2026 · 20:51 UTC. Regional openings are not confirmed assignments to the projects in this brief.

50data-center / fab openings
6hiring employers
44with published pay
13with mobility terms

6 of 6 feeds for employers represented here are current within six hours. Delayed feeds retain their last available inventory. Source freshness →

Explore all Nashville region openings →

Projects and delivery responsibilities

A partial market roster. Targets remain targets until confirmed; operating campuses provide delivery context, not evidence of a new construction award.

Meta Gallatin →

Operating · Data center · Record updated Oct 14, 2026
About 982,000 sq ft

Meta broke ground in Gallatin in August 2020, and DPR's project team topped out the first phase, two buildings of nearly one million square feet, by January 2022. Meta reported the campus serving traffic on November 14, 2024. Full build-out is a Meta target; current construction is not confirmed by a primary source.

Who is involved

Milestones

  • Reported · August 12, 2020

    Groundbreaking Source ↗

  • Reported · January 2022

    First-phase topping-out reported by DPR Source ↗

  • Reported · November 14, 2024

    Campus serving traffic Source ↗

Evidence and dates · 4 sources

More buildout briefs · Inspect our coverage · Suggest a correction