BUILDOUT BRIEFS Racine / Mount Pleasant

Racine / Mount Pleasant: projects and hiring

1 sourced project profiles, documented delivery responsibilities and current regional openings.

Sourced project records · evidence dates are listed below · Racine / Mount Pleasant market →

Hiring in Racine / Mount Pleasant

Inventory assessed Sep 26, 2026 · 03:07 UTC. Regional openings are not confirmed assignments to the projects in this brief.

0data-center / fab openings
0hiring employers
0with published pay
0with mobility terms

No matching openings are currently captured for this market. Check the official employer links in the delivery roster.

0 of 0 feeds for employers represented here are current within six hours. Delayed feeds retain their last available inventory. Source freshness →

Explore all Racine / Mount Pleasant openings →

Projects and delivery responsibilities

A partial market roster. Targets remain targets until confirmed; operating campuses provide delivery context, not evidence of a new construction award.

Microsoft Mount Pleasant / Fairwater →

Operating + construction · Data center · Record updated Sep 7, 2026

Microsoft's first facility is operating. The adjacent second facility remains under construction, with foundations, structural steel and underground utilities underway and completion targeted for 2028. Separate early earthwork supports further development; it is not a third operating facility.

Who is involved

  • MicrosoftOwner

    Individual work packages are not documented in this source. Source ↗

  • Walsh ConstructionGeneral Contractor

    Phase 2 expansion: foundations, structural steel and underground utilities. Microsoft also identifies Walsh as the current construction contact. Source ↗

  • KiewitGeneral Contractor

    A separate site-preparation package reported in September 2024; not attributed to Walsh's Phase 2 work. Source ↗

Milestones

  • Reported · July 25, 2023

    Site-preparation permits reported Source ↗

  • Reported · June 23, 2026

    First facility confirmed fully operational Source ↗

  • Target · 2028

    Second facility completion Source ↗

Evidence and dates · 2 sources