BUILDOUT BRIEFS Western North Carolina

Western North Carolina: projects and hiring

3 sourced project profiles, documented delivery responsibilities and current regional openings.

Sourced project records · evidence dates are listed below · Western North Carolina market →

Hiring in Western North Carolina

Inventory assessed Nov 11, 2026 · 01:50 UTC. Regional openings are not confirmed assignments to the projects in this brief.

8data-center / fab openings
3hiring employers
0with published pay
2with mobility terms

3 of 3 feeds for employers represented here are current within six hours. Delayed feeds retain their last available inventory. Source freshness →

Explore all Western North Carolina openings →

Projects and delivery responsibilities

A partial market roster. Targets remain targets until confirmed; operating campuses provide delivery context, not evidence of a new construction award.

Microsoft Boyd Farms →

Under construction · Data center · Record updated Sep 7, 2026

Microsoft's May 2026 update describes continuing construction at Boyd Farms. Morgan Corp. was named for initial site preparation; that relationship is not an award for all subsequent building work.

Who is involved

Milestones

  • Reported · May 2026

    Construction progress update Source ↗

Evidence and dates · 1 sources

Microsoft Hickory / Stover →

Under construction · Data center · Record updated Sep 7, 2026

The May 2026 update describes utilities and foundations, with Clayco leading the current construction phase. Ames handled earlier excavation. The announced late-June steel-work target is retained as a target, not a verified completed milestone.

Who is involved

Milestones

  • Reported · May 2026

    Utilities and foundations update Source ↗

  • Target · Late June 2026

    Start of steel work Source ↗

Evidence and dates · 1 sources

Microsoft Lyle Creek →

Under construction · Data center · Record updated Oct 24, 2026

Microsoft is building the Lyle Creek campus near Highway 16 in Catawba County. Its September 2026 update reports the first building's exterior in its final stages, with mechanical, electrical, framing and drywall work under way and further buildings starting. Whiting-Turner has been the general contractor since February 2026; Morgan Corp. led the 2024 site preparation. Microsoft publishes no capacity, investment or completion date.

Who is involved

  • MicrosoftOwner

    Individual work packages are not documented in this source. Source ↗

  • Whiting-TurnerGeneral Contractor

    Microsoft's general contractor as of February 2026. Electrical and mechanical contractors are not named. Source ↗

  • Morgan Corp.Construction Partner

    General contractor for the 2024 site preparation (excavation and rock crushing), not the current phase. Source ↗

Milestones

  • Reported · March 2024

    Construction began Source ↗

  • Reported · May 2026

    Steel installation begun, starting above-ground construction Source ↗

  • Reported · September 2026

    Mechanical and electrical work begun in the first building Source ↗

Evidence and dates · 1 sources

More buildout briefs · Inspect our coverage · Suggest a correction